New 4-Lane Arterial Road Construction – Three Oaks Extension North
A significant infrastructure project is underway in Lee County with the construction of a new 4-lane divided arterial road. This road will span 3.5 miles, connecting Daniels Parkway to the Three Oaks Parkway Extension at Fiddlesticks Canal. Upon completion, the road will serve as a vital north-south corridor, easing traffic congestion and improving connectivity between Lee County and Collier County.
Project Details:
- Total Cost: $104,915,390
- Current Status: Design Phase
- Planned Start Date: January 2024
- Estimated Completion Date: December 2029
Phases of Construction:
-
-
- Phase 1: Expected to be complete by late summer 2025.
-
- Phase 2: Construction is anticipated to begin in spring 2025 or earlier.
This Lee DOT project is critical for enhancing the region’s infrastructure and addressing the growing transportation needs of the community.
Funding Sources:
- Gas Tax
- Impact Fees
Contact Information:
For more information about the project, please reach out to:
- Contact Person: Vince Miller
- Email: vmiller@leegov.com
- Phone: (239) 533-8577
- Project Website: https://threeoaksextension.com/